Large TI in operational sortation facility. Project was built in 5 phases to allow for facility to continue to operate. 20,000 tons of steel super structure was erected for Automative Robotics platform.
The project team was awarded the SHARP designated from OSHA, one of it’s highest accolades for project safety.
Square feet:
1,097,639
Architect:
HPA
Awards:
2020 Cal/OSHA Golden Gate Award